Power reforms scheme running slow: CAG

Power ministry had budgeted Rs 12,415.04 crore during 2008-09 to 2014-15 for R–APDRP scheme which was only 43.68 percent of the envisaged amount

GN Bureau | December 22, 2016


#CAG   #power   #power generation  



The CAG has found shortcomings in the Restructured Accelerated Power Development and Reforms Programme (R-APDRP), which was to focus on reduction of losses, establishment of reliable and automated system for collection of accurate base line data and the adoption of Information Technology.

“The gross budgetary support of Rs 28,424 crore was envisaged for the scheme in the XI and XII plan periods (2008–17). Against this, ministry of Power had actually budgeted Rs 12,415.04 crore during 2008-09 to 2014-15 which was only 43.68 percent of the envisaged amount.

“R–APDRP scheme has been subsumed in Integrated Power Development Scheme since December 2014 and no separate budget for R–APDRP has been allocated after 2014–15. The actual releases during 2008–15 on R–APDRP scheme were only Rs 8,175.45 crore implying slow pace of scheme implementation,” said a CAG report.

The report said that counterpart funding was not tied up by many state utilities implementing the scheme within the prescribed period. Audit noticed that Power Finance Corporation did not maintain records of counterpart funding raised by the utilities from financial institutions. Also, instances of diversion of R-APDRP funds and overlapping of schemes were noticed in some states.

R-APDRP was launched in December 2008 as a continuation of the Accelerated Power Development and Reforms Programme (APDRP) in the XI Plan period. The programme envisaged sustainable reduction of Aggregate Technical and Commercial (AT&C) losses, establishment of reliable and automated system for collection of accurate base line data and the adoption of Information Technology in the area of energy accounting as necessary preconditions for sanctioning distribution strengthening projects.

The scheme also aimed to map all power distribution assets, index and meter all consumers to ensure that electricity supplied can be traced to the ultimate consumer thereby resulting in better billing efficiency.

Regarding programme implementation, CAG noticed that there were delays ranging up to 13 months in finalization of preparatory activities for implementation of the programme.

“Detailed Project Reports were not prepared in line with the Model Detailed Project Report, resulting in inclusion of inadmissible items of work and exclusion of required items of work in the scope of the project. Assumptions made during project formulation were not independently verified during appraisal. Instances of revision in cost of the projects without approval of the Steering Committee were noticed. In some cases, the Detailed Project Reports were appraised and approved by the Steering Committee without recommendation of State Distribution Reforms Committees in contravention of the prescribed procedure.”

It added that additional expenditure due to re-tendering and award of works to contractors at different rates for similar items of work being executed in a state were observed.

“Deficiencies in quality controls like procurement of material in deviation of specifications, failure of the items/systems leading to delay in completion of the projects and not obtaining suitable guarantees were noticed.  The efforts made to impart training to the staff of the utilities were inadequate and the purpose of training of staff was not achieved.”

Read the complete report here

Comments

 

Other News

A gender perspective on migration

Khohar, a village located in Alwar district of Rajasthan, nestled in the foothills of Aravalis, is home to 154 families, most of whom are farmers by profession. The village has a large adult population with 65 percent over the age of 18. The village educational levels are relatively low, with household h

Is the political will lacking to make Delhi`s air clean?

Is the political will lacking to make Delhi`s air clean?

For the sunset years

The New Pension Scheme (NPS), the government of India’s flagship pension scheme, has been subject to a number of important reforms in recent times. This is a welcome change from the norm wherein the government’s and the regulators’ interest in pension products is passing at best. The Pe

Who will pay the price of overpopulation?

Olden days of civilisation experienced famines and natural disasters that caused human misery. While human population was limited, natural habitats were undisturbed and abundant; so calamities of nature were absorbed without any serious consequences. However, this no longer holds true in the current

Schooling change

Jhunjhunu, in northern Rajasthan, is known for its grand havelis and the frescoes on their walls. But they weren’t on prime minister Narendra Modi’s mind when he spoke of the desert town in his Mann Ki Baat radio talk of March 2018. What he focused on, instead, were the government schools in

The road ahead

A fter mixed response from the EPC (engineering, procurement and construction) and BOT-Annuity (build, own, transfer) model, the road sector in India is exploring the Hybrid Annuity Model (HAM) for roadways construction. In HAM, 40 percent of the project cost is provided by the government as ‘const

Current Issue

Current Issue

Video

CM Nitish’s convoy attacked in Buxar

Opinion

Facebook    Twitter    Google Plus    Linkedin    Subscribe Newsletter

Twitter