RTI reveals slack progress on delayed VAG Metro Corridor

Only 70 percent civil work on its alignment and 60 percent for its 12 metro stations en-route was complete as on October 2011

ashishm

Ashish Mehta | November 16, 2011



Contrary to the claims of executing agencies, right to information (RTI) query on Mumbai’s much awaited first metro corridor  has revealed that only 70 percent civil work on its alignment and 60 percent for its 12 metro stations en-route was complete as on October 2011.

The information  stands in sharp contrast  to claims by Mumbai  Suburbs Guardian Minister, Naseem  Khan last week where he said that Metro line along  Versova- Andheri –Ghatkopar route  is likely to be commissioned by November next year.

As per the RTI reply, cost of the first metro project- a first on public private partnership (PPP), is Rs 2356 crore.

MMRDA is 26 percent stakeholder in the project. Central government is pooling in Rs 471 crore out of total amount of Rs 650 crore of Viability Gap , while balance cost of Rs 179 crore is shared by the state government as well as MMRDA.

“The authority has failed to clarify cost escalation. When work for its alignment had started in February 2008, as per the agreement , Reliance Infrastructure led consortium had claimed that it will finish work well before March 2012. However now since work has been delayed because of several reasons  there is bound to be huge escalation, but MMRDA has not bothered to give the details of the same,” says activist Anil Galgali who filed the RTI. 

Referring to its Bhoomipujan by Prime Minister Manmohan Singh on June 21, 2006 when Galgali  inquired about its target completion date he was told that ‘no deadline’ was set for VAG  completion.“This further indicates authorities’ indifference in planning  the metro in Mumbai,” he says.

Further as per MMRDA records, six people lost their lives since the inception of the project in February 2008. On May 14, 2008 Vijay Kumar, a businessman lost his life when 80 tonne piling rig fell on the auto rickshaw he was traveling in at Andheri (W).

Vinod S B Singh, the auto rickshaw driver was injured in the mishap. Due to open wires, Navin Prasad Singh was electrocuted to death near Andheri railway station during heavy rains on July 14, 2009. On March 7, 2011, dead body of Namdev Jadhav was found near Sarvodaya Hospital in a pit. The investigations for this casualty are still on. Dattatray Padekar and Pratap Padekar (both students) fell in a three meter deep pit in Sakinaka and lost their lives on April 9, 2011. On July 7, Banawar Lal a construction worker died near Navrang cinema when he fell off from a 12 meter girder.

Mumbai Metro One Pvt Ltd (MMOPL) has so far paid more than Rs 40 lakh  in compensation to the relatives of the deceased.

 

Status of Civil Work of Alignment  as per RTI query :

Pile Caps plus Rafts-  Total: 464, Complete : 449
Peers-  Total: 451,  Completed : 413

Peer Cap Construction- Total: 431, Complete :345
Peer Cap Launching- Total: 431, Complete:376

U Girder Construction- Total: 759, Complete: 665
U Girder Launching- Total: 759, Complete: 540

Station Piles- Total: 888, Complete: 760
Station Pile Caps plus Raft- Total: 298, Complete: 249
Station Pillars- Total:449, Complete: 393
 

 

Comments

 

Other News

`Low-cost Carboplatin boosts survival in aggressive breast cancer`

Adding the inexpensive chemotherapy drug Carboplatin to standard treatment significantly improves survival in patients with triple-negative breast cancer (TNBC), a clinical trial at the Tata Memorial Centre (TMC) in Mumbai has found. TNBC is an aggressive form of breast cancer and lacks

Recalling the ‘start-up’ days of a global security services firm

A quiet transformation began in Patna in 1973 when a young journalist, Dr. R.K. Sinha, inspired by the heartfelt appeal of social reformer Jayaprakash Narayan to support ex-servicemen, made a bold decision to leave his Rs 250-a-month job that led to the creation of Security and Intelligence Services (SIS).

Financing India’s Green Shift: The Rise of ESG Investing

The environment is important for everything in our lives, whether at home, in school, or any other place of work and engagement. After all, given the concerns the planet is witnessing, finding solutions is becoming tougher. In India right now, as in any other part of the world, even though there is enough

India moves up to 9th position globally in forest area

India has achieved a significant milestone in global environmental conservation, moving up to the 9th position in terms of total forest area globally, as per the Global Forest Resources Assessment (GFRA) 2025, released by the Food and Agriculture Organization (FAO) in Bali.  Union Minis

“Game” of cricket: Governance lessons from India’s favourite sport

India’s cricket journey is more than a record of sporting triumphs; it is a live case study in strategy, incentives, and equilibrium: the very foundations of Game Theory. As India prepares for its eight-match white-ball series against Australia, the world’s most-watched rivalry will again unfol

In this year of extreme rainfall, climate change has amplified deluge

Southwest Monsoon 2025 recently concluded with ‘above-normal’ rainfall to the tune of 108% of the long-period average (LPA). This is second consecutive year in the last decade to record above normal rains. Climate change has a critical role in driving the rainfall on the higher side, according

Visionary Talk: Amitabh Gupta, Pune Police Commissioner with Kailashnath Adhikari, MD, Governance Now





Archives

Current Issue

Opinion

Facebook Twitter Google Plus Linkedin Subscribe Newsletter

Twitter