Bullet Train Project: Third mountain tunnel breakthrough achieved

Three mountain tunnel breakthroughs achieved in 5 months in Palghar district

GN Bureau | June 2, 2026


#Bullet Train   #Railways  


A major engineering milestone has been achieved in the Mumbai–Ahmedabad Bullet Train Project with the successful breakthrough of the third mountain tunnel (MT-07) at Ambesari village in Dahanu Taluka of Palghar district, Maharashtra.

 
With this achievement, three mountain tunnel breakthroughs have now been completed in Maharashtra within the last five months, reflecting rapid progress in one of the most technically challenging sections of India’s first high-speed rail corridor.
 
The newly completed MT-07 mountain tunnel is 417 metres long and 14.4 metres wide, designed to accommodate both up and down tracks of the Bullet Train corridor. The tunnel was excavated through a controlled drilling and blasting method from both ends, supported by advanced engineering and safety protocols.
 
Throughout the excavation process, sophisticated monitoring systems and geotechnical instruments were deployed to ensure structural stability, worker safety and precision execution. Real-time monitoring arrangements including Surface Settlement Points (SSP), 3D targets, strain gauges and seismographs continuously monitored vibrations, tunnel behaviour and surrounding structures. Comprehensive worker-safety measures including ventilation systems, fire-safety arrangements, controlled access and continuous geotechnical supervision were maintained during tunnelling operations.
 
Previous tunnel breakthroughs in Maharashtra
The latest breakthrough builds upon earlier milestones achieved in the Maharashtra section of the project. The first mountain tunnel breakthrough (MT-05), spanning 1.5 km, was achieved near Saphale in Palghar district on 2 January 2026, marking the first successful mountain tunnel breakthrough for the Bullet Train Project in Maharashtra. This was followed by the second breakthrough (MT-06) on 3 February 2026, involving a 454-metre-long tunnel excavated using New Austrian Tunnelling Method (NATM), resulting in two breakthroughs being achieved within about one month in Palghar district.
 
Among the seven mountain tunnels under construction in Maharashtra, MT-05, MT-06 and MT-07 have now achieved breakthroughs, MT-08 (350 metre) already achieved breakthrough on 5 October 2023, MT-03 has crossed 80% excavation progress, MT-04 has reached nearly 60% progress, while MT-01 and MT-02 are progressing steadily. Of the total eight mountain tunnels in the Mumbai–Ahmedabad Bullet Train Project, seven are located in Palghar district of Maharashtra and one in Valsad district of Gujarat, where tunnelling work has already been completed.
 
All three mountain tunnels between Vapi and Boisar Bullet Train stations have been successfully excavated. The Mumbai–Ahmedabad Bullet Train corridor passes through an important industrial region between Boisar in Maharashtra and Vapi in Gujarat, where construction work is progressing rapidly. The route between these two cities include three (03) mountain tunnels (MT 08, MT-07 & MT-06).
 
The Mumbai–Ahmedabad Bullet Train Project continues to drive adoption of advanced tunnelling, monitoring and construction technologies, strengthening India’s capabilities in high-speed rail infrastructure and laying the foundation for safe, modern and future-ready rail mobility.

Comments

 

Other News

Cabinet approves Mobile Phone Manufacturing Scheme

The union cabinet chaired by PM Narendra Modi has approved the Mobile Phone Manufacturing Scheme (MPMS) with a budgetary outlay of Rs 62,500 crore. It aims to further scale up the production, deepen domestic value addition, strengthen supply chain resilience, enhance global competitiveness. It

Building infrastructure is only half the job

Recent stories of stolen railway wires, disappearing communication towers and missing public infrastructure are often treated as bizarre law-and-order failures of India. Yet they raise a more fundamental question. Why does the State often discover the disappearance of a public asset only after it has alrea

New Delhi’s Indo-Pacific strategy enters a new phase

India appears to be investing fresh dynamism in its Indo-Pacific strategy. At the time when the US, under president Donald Trump, has adopted a conciliatory approach towards China and has changed the name of America’s Indo-Pacific Command to just Pacific Command, India has quietly moved towards con

CAG flags major fiscal lapses in Maharashtra

Maharashtra`s fiscal management has come under sharp scrutiny after the Comptroller and Auditor General (CAG) of India, in its State Finances Audit Report for 2024-25, flagged significant budgetary inefficiencies, accounting irregularities, understatement of key fiscal indicators and widespread governanc

The health sector research we are not doing

Some neglect is loud. This kind is quiet. It sits in research never commissioned, data never collected, questions never asked. In South Asia, that quiet has let the region’s worst health problems stay understudied, underfunded, and out of sight of those who could act.  

Study flags accessibility and last-mile challenges on Mumbai Metro Aqua Line

Mumbai Metro Line 3 (Aqua Line), the city`s first fully underground metro corridor and one of its largest public transport investments, represents a major engineering achievement and has been widely welcomed by commuters. However, the overall commuter experience continues to be constrained by accessibili

Upcoming Conferences





Archives

Current Issue

Opinion

Facebook Twitter Google Plus Linkedin Subscribe Newsletter

Twitter