Why pay an extra Rs 3.9 lakh crore?

That's the additional cost of imported n-reactors

eassarma

eas sarma | May 4, 2012



Dear Dr. Manmohan Singh,

Subject:- High cost of imported nuclear reactors at the expense of the Indian tax payer

Ref.: 1  My letter dated 17-12-2011 addressed to you
    2 Reported statement of Secretary (DAE) on the high cost of imported nuclear power reactors
 
In addition to pointing out the inherent dangers of nuclear power, I had written to you earlier, vide my letter cited above, on the huge contingent liability that the imported nuclear reactors will impose on the Indian tax payer, as a result of the diluted nuclear civil liability law that your government has enacted. I enclose a copy of that letter for your ready reference. If Fukushima provides any indication, the contingent liability will be in excess of Rs 33 crore per MW. This is over and above the high capital cost of imported nuclear power reactors being purchased on a nomination basis, without any competitive bidding and the high cost of the imported fuel that goes along with the reactors.

The proposal of your Ministry (Dept. of Atomic Energy) to set up 60,000 MW of nuclear power capacity based on imported reactors will cost the nation heavily, diverting its scarce resources from more pressing development and welfare programmes. I feel distressed that the government should display a total sense of indifference to the obvious pitfalls in the nuclear power development plan mooted by DAE!

In this connection, I enclose here a news report of a recent statement made by the outgoing Secretary (DAE) on the huge capital cost differential between indigenously made reactors and the imported ones.

According DAE's own admission, the capital cost of an indigenously manufactured power reactor is around Rs 8.5 crore per MW, compared to Rs 15 crore per MW) in the case of imported reactors. The cost estimate of Areva's reactors being set up in Finland has already touched Rs 24 crore per MW.

Even going by the lower cost figure cited by DAE for imported reactors, the capital cost differential between indigenous and imported reactors would work out to Rs 6.5 crore per MW! Since DAE has programmed to set up 60,000 MW of nuclear capacity by ordering for imported reactors, the total capital cost implication of this will be around Rs 3,90,000 crore!! This will be the additional cost that the Indian tax payer will be paying as a result of the non-transparent purchases being made by DAE to help the foreign MNCs to sustain their respective businesses which have otherwise become stagnated due to the freeze imposed by the western nations on setting up new nuclear power projects in their own countries. In other words, India will be charging its own people heavily and expose them to the dangers of an unsafe technology, to help the western MNCs to prosper and the western nations to provide employment to their own citizens!

Placing orders on the foreign reactor suppliers without going through the competitive bidding route amounts to a serious impropriety on the part of DAE. The cost of this impropriety far exceeds the loss on account of 2G spectrum scam, the captive coal block scam, the S-Band spectrum scam and the mining scams! Certainly, as a concerned citizen, I would demand an independent enquiry into the cost burden that your Ministry has imposed on the public exchequer not only by placing orders on foreign nuclear reactor suppliers but also insulating them from accident liabilities by enacting a law and rules that have shifted the liability burden from the suppliers to the Indian tax payer.

I have not quantified here the additional costs that India will incur on imported nuclear fuel, apart from the fact that DAE will also be jeopardising India's energy security by committing the country to long-term dependence on foreign reactors and fuel.

I feel particularly distressed that your government should repeatedly mock at the meagre food subsidies being given to the poorest of the poor in the country, in the name of “good economics' and, at the same time, without batting an eye lid, dole out billions of rupees of subsidies to the foreign reactor-supplier MNCs both openly and clandestinely. It is all the more disturbing that your government should refuse to look at several cost effective, environmentally benign alternatives to nuclear power, just to help the foreign MNCs.

I am marking a copy of this letter to C&AG for auditing the reactor deals that DAE has already signed and proposing to sign so that C&AG may apprise the Parliament of the far reaching implications of what DAE is doing.

Meanwhile, I would request you, as the Minister in charge of DAE, to freeze all new nuclear power projects based on imported reactors, pending an independent enquiry.

Regards,
Yours sincerely,

E.A.S.Sarma
Former Secretary to GOI
Visakhapatnam.

(This letter was sent to the PM on May 1, 2012)

Comments

 

Other News

Voting by tribal communities blossoms as ECI’s efforts bear fruit

The efforts made by the Election Commission of India (ECI), over last two years, for inclusion of Particularly Vulnerable Tribal Groups (PVTG) communities and other tribal groups in the electoral process have borne fruit with scenes of tribal groups in various states/UTs participating enthusiastically in t

GST revenue for April 2024 at a new high

The gross Goods and Services Tax (GST) collections hit a record high in April 2024 at ₹2.10 lakh crore. This represents a significant 12.4% year-on-year growth, driven by a strong increase in domestic transactions (up 13.4%) and imports (up 8.3%). After accounting for refunds, the net GST

First Magahi novel presents a glimpse of Bihar bureaucracy a century ago

Fool Bahadur By Jayanath Pati (Translated by Abhay K.) Penguin Modern Classics, 112 pages, Rs 250 “Bab

Are EVs empowering India`s Green Transition?

Against the backdrop of the $3.5 billion Production-Linked Incentive (PLI) scheme launched by the Government of India, sales of Electric Vehicles (EVs) are expected to grow at a CAGR of 35% by 2032. It is crucial to take into account the fact that 86% of EV sales in India were under the price bracket of $2

When Nandini Satpathy told Biju Patnaik: ‘I’ll sit on the chair you are sitting on’

Nandini Satpathy: The Iron Lady of Orissa By Pallavi Rebbapragada Simon and Schuster India, 321 pages, Rs 765

Elections 2024: 1,351 candidates in fray for Phase 3

As many as 1,351 candidates from 12 states /UTs are contesting elections in Phase 3 of Lok Sabha Elections 2024. The number includes eight contesting candidates for the adjourned poll in 29-Betul (ST) PC of Madhya Pradesh. Additionally, one candidate from Surat PC in Gujarat has been elected unopp

Visionary Talk: Amitabh Gupta, Pune Police Commissioner with Kailashnath Adhikari, MD, Governance Now


Archives

Current Issue

Opinion

Facebook Twitter Google Plus Linkedin Subscribe Newsletter

Twitter