Irregularities spotted in Kudankulam n-power project

CAG finds that revenue loss was suffered

GN Bureau | December 29, 2017


#nuclear power   #Kudankulam   #CAG   #nuke   #Nuclear Power Corporation of India Limited  


The Comptroller and Auditor General (CAG) has spotted irregularities in Kudankulam nuclear power projects, units 1 and 2.

 
The scheduled date of completion was postponed from October 30, 2007 to December 31, 2011 for Unit I and October 30, 2008 to December 31, 2012 for Unit II, due to delayed completion of different activities, of which many were attributable to the M/s Atomstroyexport (ASE), a company responsible for undertaking the Russian scope of work.
 
“However, there was no revision of schedule of repayment of the Russian credit. This resulted in start of repayment of Russian credit, before revenue generation, causing an additional interest burden on NPCIL to the tune of Rs 449.42 crore,” said the CAG report
 
Nuclear Power Corporation of India Limited (NPCIL) had to resort to external borrowings at a higher interest rate due to non- provisioning for erection reserve supply contracts while availing Russian credit, which was available at a cheaper rate. This resulted in additional interest cost amounting to Rs 76.02 crore.
 
NPCIL availed term loan of Rs 1,000 crore from HDFC Bank Limited in violation of CVC’s guidelines on tendering, it said.
 
NPCIL, while fixing tariff for power, did not consider two components, i.e., ‘interest on foreign debt’ and ‘interest on domestic borrowings’, though these were actually incurred and paid. This resulted in short realisation of revenue to the tune of Rs 90.63 crore during pre-commercialisation period.
 
The report said that Unit I of KKNPP was shut down from 24 June 2015 to 31 January 2016 for 222 days as against the planned period of 60 days. This was due to decision of NPCIL to shut down the plant and execute the refuelling work on its own without evaluating its technical competency. The extended shutdown resulted in revenue loss of Rs 947.99 crore to the NPCIL.
 
Unit I and Unit II of KKNPP started commercial operation after a delay of 86 months and 101 months respectively. The delays were primarily due to shifting of work from Russian scope to Indian scope; in execution of work and in submission of working documents/supply of equipment/materials by ASE; delays due to design changes; erection delays and additional works. The delay in completion have also resulted in cost overruns. NPCIL did not initiate any claim for recovery of additional expenses of Rs  264.79 crore which were caused due to delayed completion of works by ASE.
 
As against the original value of $29 million (Rs 131.66 crore), NPCIL incurred an amount of $50.91 million (Rs 231.13 crore) for supply of same equipment in a rearranged contract leading to extra expenditure of Rs 99.47 crore.
 
“No claim was raised by NPCIL, on ASE, for turbine of Unit I which was damaged due to manufacturing defects and Rs 12.76 crore was incurred on repairs and replacement of turbine rotors. It also resulted in non- generation of electricity and consequently loss of revenue amounting to Rs 53.73 crore,” said the CAG report.
 
It added that NPCIL neither assessed the extra payment/loss due to non supply/defective supply of materials by ASE nor did it initiate any action for recovery/adjustments for the same.
 
NPCIL did not raise/pursue claims for liquidated damages worth Rs 463.08 crore from ASE even though during the same time, it was borrowing funds and paying interest to discharge debt obligations including from ASE.
 
The work of erection and commissioning of Nuclear Steam Supply System and Turbo Generator was shifted from the Russian scope to the Indian scope for achieving the stated purpose of optimization of man power cost by way of reduction in man-months of Russian specialist for supervision at the site. This was done without any cost-benefit analysis, which not only resulted in delays in completion of the project but also ended up in NPCIL incurring an extra expenditure of Rs 706.87 crore for the work, it said.

Comments

 

Other News

“World headed towards stagflation; India must take care of the poor”

As the post-pandemic fallout and geopolitical uncertainty slows down global economies and sanctions against some nations, energy crisis and inflation are adding to the troubles, India is projected to be decoupled from world economy and fare better. To check if this belief really holds water, in the latest

The changing nature of CSR in India

With the advent of globalization came a new set of challenges for corporations, notably the duty of ensuring the well-being of all stakeholders while also protecting the planet`s natural environment. Although we are dedicated to a faster and more inclusive rate of growth, it is equally imperative that we f

BMC commissioner Chahal conferred with hon. doctorate

BMC commissioner and administrator Iqbal Singh Chahal has been conferred with a Honorary Doctor of Science Degree (honoris causa) by Guru Nanak Dev University in Amritsar, Punjab. Chahal was conferred the degree during the 48th convocation of the University in Amritsar at the hands of Punjab

Sebi to have two-track approach on ESG

Securities and Exchange Board of India (Sebi) aims to use a two-track approach on environmental social and corporate governance (ESG). Addressing a conference on ‘ESG for Atmanirbhar Bharat` in Mumbai, Sebi chairperson Madhabi Puri Buch said that that there should not be a single carbo

Accuracy more important than speed in news: Anurag Thakur

Presenting authentic information is the prime responsibility of media and that facts should be properly checked before they are put in the public domain, union minister of information and broadcasting Anurag Thakur has said. “While speed with which the information is transmitted is imp

FM concludes pre-budget consultations

Union minister for finance and corporate affairs Nirmala Sitharaman has concluded the pre-budget consultation meetings for Budget 2023-24 that were held from November 21 to 28 in the virtual mode. More than 110 invitees representing seven stakeholder groups participated in eight meetings sch

Visionary Talk: Amitabh Gupta, Pune Police Commissioner with Kailashnath Adhikari, MD, Governance Now


Archives

Current Issue

Opinion

Facebook    Twitter    Google Plus    Linkedin    Subscribe Newsletter

Twitter