Railway projects in Maharashtra make rapid progress

2,360 km length of railway lines commissioned in state by March 2025 at a cost of Rs 39,407 crore

geetanjali

Geetanjali Minhas | August 1, 2025 | Mumbai


#Railway   #Maharashtra   #Infrastructure  


The progress of railway projects in Maharashtra is rapid as the state government is giving full support for improving connectivity, minister of railways Ashwini Vaishnaw stated this in the Rajya Sabha on Friday.
 
“There was a push back in many railway connectivity projects from 2019 to 2022 due to the then state government’s policies. This had major impact on Railway and Metro projects, especially the high speed corridor. However, since 2022, there is good support for improving connectivity in Maharashtra,” the minister said in reply to an unstarred question by Sanjay Raut.

Maharashtra is covered under the jurisdiction of four railway zones – Central Railway, South Central Railway, South East Central Railway and Western Railway. For these zones, an allocation of Rs 3,751 crore has been made for the financial year 2025–26, out of which an expenditure of Rs 813 crore has been incurred so far.

Mumbai Urban Transport Project
To improve the connectivity in Mumbai suburban area and to meet the future demands of passengers, Mumbai Urban Transport Project (MUTP)-II costing Rs 8,087 crore, MUTP-III costing Rs 10,947 crore and MUTP-IIIA costing Rs 33,690 crore have been sanctioned. 

These projects include following works in Mumbai Suburban Area:

S. No. // Name of project // Cost (Rs in crore)
1    6th Line Mumbai Central-Borivali (30 km)      919
2    Extension of Harbour Line Goregaon-Borivali (7 km)    826
3    Virar-Dahanu Road 3rd & 4th Line (64 km)    3587
4    5th & 6th Line CSTM-Kurla (17.5 km)    891
5    Panvel-Karjat Suburban Corridor (29.6 km)    2782
6    Airoli-Kalwa (elevated) Suburban Corridor link (3.3 km)    476
7    5th & 6th line Borivali-Virar (26 km)    2184
8    4th line between Kalyan-Asangaon (32 km)    1759
9    3rd & 4th line between Kalyan-Badlapur (14.05 km)    1510
10    Kalyan Yard-Segregation of Main Line & Suburban    866
11    Vasai bye pass line (Double line) between Naigaon and Juchandra (5.73 Km)    176
12    Trespass Control (34 locations)    551

Further, as on April 1, 2025, 38 Railway projects of total length of 5,098 Km, costing Rs 89,780 crore falling fully/partly in Maharashtra are at various stages of planning and implementation, out of which 2,360 km length has been commissioned and an expenditure of Rs 39,407 crore has been incurred up to March, 2025.

Some of the major infrastructure projects taken up and falling fully/partly in Maharashtra are:
S. No. // Name of the project    // Cost (Rs In crore)
1    Ahmednagar-Beed-Parle Vaijnath New Line (261 Km.)    4,957
2    Baramati-Lonand New Line (64 Km.)    1,844
3    Wardha-Nanded New Line (284 Km.)    3,445
4    Dhule (Borvihir)-Nardana New Line (51  Km.)    1,171
5    Manmad-Indore New Line (309 Km.)    16,321
6    Wadsa-Gadchiroli New Line  (52 Km)    1,886
7    Jalna -Jalgaon New Line (174 Km.)    5,804
8    Pune-Miraj-Londa  Doubling (466 Km.)    6,463
9    Daund Manmad  Doubling (236 Km.)    30,376
10    Mudkhed - Medchal & Mahbubnagar - Dhone section Doubling (417 Km.)    4,686
11    Hotgi-Kudgi-Gadag Doubling  (284 Km.)    2,459
12     Kalyan-Kasara - 3rd line (68 Km.)    1,433
13    Wardha -Nagpur 3rd line (76 Km.)     698
14    Wardha-Ballarshah 3rd line (132 Km.)    1,385
15    Itarsi- Nagpur 3rd line (280 Km.)    2,450
16    Manmad Jalgaon 3rd line (160 Km.)    1,677
17    Kazipet -Ballarshah - 3rd line (202 Km.)    3,183
18    Rajnandgaon-Nagpur 3rd line (228 Km.)    3,545
19    Wardha-Nagpur 4th line (79 Km.)    1,137
20    Jalgaon-Manmad 4th Line (160 Km)    2,574
21    Bhusawal-Khandwa 3rd & 4th Line (131 Km.)    3,285

Further, the prestigious Mumbai-Ahmedabad High Speed Rail (508 km) project at a cost of Rs 1,08,000 crore has gathered momentum in Maharashtra. Now 100% land acquisition has been completed. Works of bridges, aqueducts etc. have been taken up.

Western Dedicated Freight Corridor (WDFC) from Jawaharlal Nehru Port (JNPT) to Dadri (1506 km) has been taken up at a cost of  ₹ 51,101 crore is also passes through Maharashtra. About 178 route Km of western DFC is situated in Maharashtra which is about 12% of overall route length of western DFC. 76 Km of this project from New Gholvad to New Vaitarna in Maharashtra has already been commissioned. Balance works have been taken up. Connectivity of WDFC to JNPT will boost the capacity to handle cargo and container traffic from port to Delhi NCR.

Station Development in Maharashtra
So far, 1337 stations including 132 stations in the State of Maharashtra have been identified for development under Amrit Bharat Station scheme. Development works at railway stations under Amrit Bharat Station Scheme in the State of Maharashtra have been taken up at a good pace. Till now, phase-I works of 15 Amrit Bharat stations in Maharashtra have been completed under this scheme. Development, upgradation and modernisation of all stations, including Amrit Bharat Station Scheme, is generally funded under Plan Head-53 ‘Customer Amenities’ and details of allocation and expenditure under Plan Head-53 are maintained Zonal Railway-wise and not work-wise, or station wise or state-wise.

2,360 km length of railway lines commissioned up to March 2025
As on 1st April, 2025, 38 projects (11  New Lines, 02 Gauge Conversion and 25 Doubling), of a total length of 5,098 km, costing Rs 89,780 crore, falling fully or partly in Maharashtra, are sanctioned, out of which 2,360 km length has been commissioned and an expenditure of  ₹39,407 crore has been incurred upto March 2025, minister of railways Ashwini Vaishnaw stated in reply to an unstarred question by Dhananjay Bhimrao Mahadik in the Rajya Sabha on Friday.
 
During the last three years (FY 2022-23, 2023-24, 2024-25) and the current FY, 27 Multi-tracking  project of total length 1,991 km, costing approx. Rs 47,126 crore falling fully/ partly in Maharashtra, have been sanctioned.  

These multi-tracking projects will enhance line capacity, provide additional passenger and freight traffic, enable faster movement of goods and services, reduce operational bottlenecks, improve logistics efficiency, increase in direct and indirect employment opportunities for the people of the region, develop tourism industry and increase industrial activities in the region. 

Further, during  the last three years i.e. FY 2022-23, 2023-24, 2024-25 and the current FY, 94 surveys (26 New Line, 2 Gauge Conversion and 66 Doubling) of total length 7979 Km. falling fully/ partly in the State of Maharashtra have been sanctioned under PM Gati Shakti National Master Plan.

In Maharashtra, entire existing Broad Gauge (BG) network (5,938 Route Km.) has been electrified.  All New Line projects are being sanctioned and constructed with electrification.

Comments

 

Other News

BRICS at 20: From economic weight to global influence

This year marks 20 years of BRICS, with India set to host the grouping’s leaders’ summit this weekend. The anniversary offers an opportune moment to assess BRICS’ growing importance at a time when the effectiveness of global governance and the credibility of multilateralism are under in

Former president Ram Nath Kovind on some of his unforgettable journeys

Triumph of the Indian Republic: My Life, My Struggles By Ram Nath Kovind Rupa Publications, 400 pages, Rs 795   All our presidents so far stand out, each for a different reason. Ram Nath Kovind, the 14th president of India, from 2017 t

Uday Kotak on history, Indian economy, growth and more

Pathbreakers: How 10 Visionary Leaders Transformed India by award-winning journalists  By Sucheta Dalal and Debashis Basu Rupa Publications, 304 pages, Rs 695  

₹5,000 crore saved from suspected financial fraud

In a significant gain for citizen protection in the digital economy, the Department of Telecommunications (DoT) has helped prevent suspected cyber fraud losses of more than ₹5,000 crore through its Financial Fraud Risk Indicator (FRI) within fifteen months of its launch on May 22, 2025. This money did

Capital acquisition proposals worth Rs 1.10 lakh crore for defence forces cleared

The Defence Acquisition Council (DAC), under the chairmanship of Raksha Mantri Rajnath Singh, on Monday accorded Acceptance of Necessity (AoN), that is, in-principle administrative approval to various acquisition proposals of the defence forces at an estimated cost of about Rs 1,10,000 crore.

How Rafi, Raj Kapoor helped pave the way for a great uranium deal

There`s a certain moment in diplomacy that`s too personal to be captured in a communiqué, too small to make the front page, but more revealing than the front page. This week, prime minister Narendra Modi reached Tashkent and, amid the pomp of state visits, managed to evoke the old Bollywood tunes

Upcoming Conferences



-->

Archives

Current Issue

Opinion

Facebook Twitter Google Plus Linkedin Subscribe Newsletter

Twitter