Biting the bullet train

If India is to launch its first bullet train in five years, it will need meticulous planning to meet a series of challenges

vishwas

Vishwas Dass | October 16, 2017 | New Delhi


#Narendra Modi   #Bullet Trains   #Ahmedabad-Mumbai high-speed rail   #Shinzo Abe   #Japan   #Piyush Goyal  
Photo courtesy: www.nhsrcl.in
Photo courtesy: www.nhsrcl.in

If all goes well, India’s first high-speed train would zip by in  December 2023. In fact, railways minister Piyush Goyal is even confident that the 508-km Ahmedabad-Mumbai high-speed rail (HSR) project would be completed much before that, by August 2022 – on the country’s 75th independence anniversary. It remains to be seen if the National High Speed Rail Corporation Limited (NHSRCL), the executing agency of the project, would be able to meet either of the deadlines.

Many former railway board members and some railway experts believe that it would be unfair to expect the NHRCL to launch the project before the deadline due to a plethora of challenges like working on the new Shinkansen HSR technology.

READ: Why bullet trains are unsuitable for India


Railway officials say it is one thing to set up multiple deadlines on paper and quite another thing to execute them; meticulous planning is needed to accomplish the target.

Also, questions are being raised whether the bullet train would be able to get thousands of passengers daily to make the project financially viable. As per a report by the IIM Ahmedabad, the high-speed train requires 90,000-1,20,000 passengers per day to make it financially viable.

Key features

Length 508 km, double-line through Maharashtra (156 km) and Gujarat (351 km) and UT of Dadra and Nagar Haveli (2 km)

Longest tunnel of 21 km including undersea tunnel of 7 km (Thane Creek)

12 stations: Mumbai, Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand, Ahmedabad and Sabarmati. The only underground station will be in Mumbai, others elevated.

Maximum design speed: 350 kmph

Maximum operating speed: 320 kmph

Journey time: 2.07 hrs (limited stops), 2.58 hrs (stopping at stations) vis-a-vis existing train travel time of 7-8 hours

Some facts about Mumbai-Ahmedabad HSR

Project cost estimated at '1,08,000 crore. Nearly entire corridor elevated for safety and land economy

81% of the project cost borne by the Japanese soft loan at 0.1% per annum with repayment period 50 years, including grace period of 15 years.

Four sub-groups with representatives from the Indian and Japanese industry, DIPP, NHSRCL and JETRO will identify potential items or activities for Make in India initiative

High Speed Rail Training Institute at Vadodara to train 4,000 staff for operations and maintenance

The project will create 20,000 construction jobs. There will be 4,000 direct jobs for operations and 20,000 indirect jobs

Shinkansen technology will be used, known for reliability and safety with proven track record of more than 50 years

Punctuality record for the technology is less than a minute with zero fatality since its launch in 1964 in Japan

Project comes with technical support and handholding of the Japanese. It will ensure complete transfer of know-how to Indians for future projects

It will give a boost to urban and industrial development along the corridor

But a former member (traffic) of the railway board, on condition of anonymity, says, “There is no guarantee that people who commute through road and air would switch to the high-speed train, which is not going to be very cheap. People who have enough time to reach Mumbai from Ahmedabad will avoid paying a hefty fare for the bullet train and would rather travel by a conventional train.”

Agrees Sunil Kumar, former advisor (safety) and additional member, Railway Board. He says that the ridership depends on the fare structure because middle-class people will only use the bullet train if it comes with an attractive fare tag.

“The HSR is not going to be a financially attractive proposition but if the government wants to provide a new technology to the people who can afford it; it is the suitable time,” says the former member (traffic).

READ: Achal Khare, MD, National High Speed Rail Corporation on the bullet train roadmap


He further says that fixing the alignment for the 508-km project itself is a daunting task. Construction work can only begin after the design and plan are prepared, which would take at least two years.

“If everything falls in place, which means getting the material and technical expertise, it would take at least seven years after all preparatory works are done to launch the high-speed train. Land acquisition is a complex issue despite the fact that a majority of the project is on an elevated corridor. Consultations would have to be done with the locals for land acquisition. Social and environmental assessment would also require time,” he adds.

The former member (traffic) also says that the bullet train will not generate profit in its initial years mainly because of the fare and availability of other modes of transportation on the proposed route.

A senior railway official believes that the biggest challenge would be to ensure transfer of technology and promote ‘Make in India’ by manufacturing key components of the bullet train in the country.

“By the time the bullet train will be unveiled a production facility should be established in India, otherwise it would take years to give a push to the ‘Make in India’ initiative. The Japanese have certain reservations on ‘Make in India’ because they intend to promote their own industry. Since, the project depends on a Japanese loan, India is bound for sourcing the components from Japan. In the tenders, only Japanese companies would be able to participate in some of the sectors like rolling stock. There are certain areas where Indian companies would participate. There will be joint ventures between Indian and Japanese companies,” he says.

VN Mathur, former member (traffic), railway board, says that between 2004 and 2017, China had already developed 22,000 km of high-speed rail lines. At present, Morocco is building its HSR network. “Though India is already late in introducing the HSR, it is the apt time to execute it but the authorities will have to execute it meticulously to get the work completed within deadline,” he says.

Sunil Kumar adds, “The alignment is completely new which the Indian Railways has never seen before. Besides, the maintenance cost of the bullet train is going to be very high. To keep any technology snag-free requires intensive work and culture of maintenance.”

Moreover, he adds, NHSRCL needs a person like E Sreedharan to have its first high-speed train by December 2023, which comes with many challenges. “If any legal issue comes up for land acquisition, it has to be expeditiously resolved, otherwise the deadline would get affected. Elevated corridors reduce the requirement of land but resettlement of affected people often takes time,” Kumar says.

vishwas@governancenow.com

(The article appears in the October 31, 2017 issue)

 

Comments

 

Other News

Harnessing the demographic capital: how effective are skilling programmes?

Probing data concerning increased job creation and the decline in unemployment has been holding the attention of economists and been subject of discussions in several think tanks in the preceding months. The NITI Aayog reports that 3.53 million new jobs were created between September 2017 and February 2018

It`s time to Unlock now, with economic focus

With Lockdown 4 ending Sunday, the home ministry has issued new guidelines to fight COVID-19 and for phased re-opening of areas outside the Containment Zones. The guidelines, issued based on extensive consultations held with states and UTs, will be effective from June 1 till June 30. The first phase of reo

Small kitchen gardens turn saviours for Gujarat tribal families

When the whole world is fighting COVID-19, food and nutrition security has become a major issue. The pandemic has aggravated the existing food crisis in India, especially in rural and tribal regions. There has been less availability of fresh foods in most parts of the country, and the tribal community has

India will set example of post-Covid-19 economic revival: Modi

India is determined to “set an example” for the rest of the word in the post-pandemic economic revival, prime minister Narendra Modi has said, underling the need to become self-reliant. “There is also a widespread debate on how the economies of various countries, including

3,543 ‘Shramik Special’ trains transport 48 lakh people in 26 days

Close to 48 lakh migrant labourers have been able to reach home from the cities they were working in, as the Indian Railways have run a total of 3,543 “Sharmik Special” trains from May 1. Following the home ministry order regarding the movement by special trains of migrant worker

How Jeevan Raths have helped 52,000 migrants in Maharashtra

Before the novel coronavirus hit it, Mumbai about 10-12 lakh labourers from elsewhere had made it their home. The figure for the state of Maharashtra was another 18-20 lakh. As the pandemic spread and the Maximum City emerged as the worst-hit place in India, all economic activities came to an end, and with



Archives

Current Issue

Opinion

Facebook    Twitter    Google Plus    Linkedin    Subscribe Newsletter

Twitter