Know more about Project 75

Kalvari was the first of the Indian Navy’s Scorpene class stealth submarines being built under the Project 75

GN Bureau | December 15, 2017


#Narendra Modi   #Project 75   #Kalvari   #Indian Navy  


When prime minister Narendra Modi dedicated Kalvari submarine to the nation, it was significant for more than one reason. Not only did the submarine enhance India’s capability as a blue water navy, it also highlighted Project 75 that focused on a major exercise to build six submarines.

Project 75 faced innumerable challenges and the first of the six submarines showed that the effort is still on track. These submarines would form the core of the navy’s submarine arm for the next two decades.

The Cabinet Committee on Security on July 12, 1999, accorded approval for a 30 year plan for series construction of submarines for Indian Navy in two phases, with second phase to be indigenous.

The delay in construction of Project 75 submarines is attributed to teething problems in absorption of new technologies, delay in augmentation of industrial infrastructure at Mazagaon Dockyard Ltd. (MDL) and delay in procurement of various MDL procured items, parliament was informed in December 2014.

“Government reviews the progress of Project 75 and other ongoing ship construction projects periodically. The reasons for delay in each case are individually assessed. Some major reasons of delay are infrastructure constraints at shipyards, difficulties in import of warship grade steel, delay in indigenous development of warship grade steel and absorption of new technologies etc. These reasons have attributed to different cost escalations in different projects,” then defence minister Manohar Parrikar said in a written reply to Dharmendra Yadav and ShrirangappaBarne in the Lok Sabha.

What exactly is Project 75?

Project 75 was for construction of six submarines based on a Western design and six submarines of a design sourced from Eastern origin (Russia included) under Project 75(I) were to be constructed with the participation of the Indian industry both, private and public, explained Indian Defence Review.

For the project, a contract with Thales/DCNS International was concluded to construct six submarines based on the Scorpene design at MDL in October 2005. The submarines are highly sophisticated and of contemporary design. The weapons envisaged on these platforms are state-of-the-art torpedoes and the Exocet anti-ship missile.

Things don’t look good for Project 75(I), with indiandefencereview.com saying that the project has been inordinately delayed.

As far as Project 75 are concerned, it seems to be on track.

On July 21, 2017, Subhash Bhamre, minister of state in the defence ministry, told the Lok Sabha that six submarines are under construction under Project 75 at the Mazagon Dock Shipbuilders Ltd, Mumbai.

“The first submarine is scheduled to be delivered in August, 2017. The second submarine was launched in January 2017 and is scheduled for delivery in December, 2017. The induction of the Kalvari class submarines will enhance the capabilities of the Indian Navy to meet envisaged threats and missions,” said Bhamre.

The submarine dedicated to the nation on Thursday was handed over for extensive sea trials. Only after extensive tests, is it being put to use.

PIB in April 2015 reported that Kalvari, first of the Indian Navy’s Scorpene class stealth submarines being built under the Project 75, under collaboration with M/s DCNS, France, had achieved a major milestone with her ‘undocking’ at the Mazagon Dock Limited (MDL).

The project 75, which by then had already seen a delay of almost 40 months, was brought on track and the delivery schedule for the successive submarines was reduced. Parrikar had then asked the defence public sector yards viz. Mazagon Docks Limited and Goa shipyard to double their production in the coming three years.             

The Scorpene submarines would pack a potent punch. She would be equipped with anti-ship missiles and long range guided torpedoes along with modern sensor suite.
 

Comments

 

Other News

Reopening: Old guidelines extended to November

As the Covid-19 situation continues to improve in India, the ministry of home affairs (MHA) has decided to continue the Guidelines for Reopening, which have already done away with nearly all of Lockdown restrictions in areas outside the containment zones. The MHA issued an order Monday and e

India records lowest new cases in three months

After a scare in September with the number of daily fresh cases inching above 90,000, India seems to have gone down the peak, with several key parameters giving cause for relief just in time for the annual festive season. The new confirmed cases in the 24 hours to Tuesday morning have fallen below 36,500 (

India’s case fatality rate lowest since Janata curfew

The annual festive season has brought good news for India: the country’s case fatality ratio has gone down to touch 1.5 percent, and the number of deaths per day has dipped below 500 in the 24 hours to Monday morning – bringing the situation closer to the number before the lockdown was imposed

“Script is the real hero”

Basking in the success of the new web series, ‘Scam 1992: The Harshad  Mehta Story ’,on SonyLIV, the OTT platform from Sony stable where the lead actors are new faces, NP Singh, MD and CEO of Sony Pictures Networks, has said that the script is the new hero. He credited the s

India’s active cases below 10% of total cases for three days

India’s trend of steadily decreasing active cases continues unabated. The number of Active Cases has remained below 10% of the total cases for the last three days, suggesting only one in 10 cases is active Covid-19 patient. The active cases comprise merely 9.29% of the total positive c

Cabinet clears bonus for non-gazetted employees

The union cabinet chaired by prime minister Narendra Modi on Wednesday gave its approval to pay productivity linked bonus (PLB) for 2019-20 to 16.97 lakh non-gazetted employees of commercial establishments like Railways, Posts, Defence, EPFO, and ESIC, with a financial implication of Rs.2,791 crore.

India Police Virtual Summit and Awards 2020

Archives

Current Issue

Opinion

Facebook    Twitter    Google Plus    Linkedin    Subscribe Newsletter

Twitter