Know more about Project 75

Kalvari was the first of the Indian Navy’s Scorpene class stealth submarines being built under the Project 75

GN Bureau | December 15, 2017


#Narendra Modi   #Project 75   #Kalvari   #Indian Navy  


When prime minister Narendra Modi dedicated Kalvari submarine to the nation, it was significant for more than one reason. Not only did the submarine enhance India’s capability as a blue water navy, it also highlighted Project 75 that focused on a major exercise to build six submarines.

Project 75 faced innumerable challenges and the first of the six submarines showed that the effort is still on track. These submarines would form the core of the navy’s submarine arm for the next two decades.

The Cabinet Committee on Security on July 12, 1999, accorded approval for a 30 year plan for series construction of submarines for Indian Navy in two phases, with second phase to be indigenous.

The delay in construction of Project 75 submarines is attributed to teething problems in absorption of new technologies, delay in augmentation of industrial infrastructure at Mazagaon Dockyard Ltd. (MDL) and delay in procurement of various MDL procured items, parliament was informed in December 2014.

“Government reviews the progress of Project 75 and other ongoing ship construction projects periodically. The reasons for delay in each case are individually assessed. Some major reasons of delay are infrastructure constraints at shipyards, difficulties in import of warship grade steel, delay in indigenous development of warship grade steel and absorption of new technologies etc. These reasons have attributed to different cost escalations in different projects,” then defence minister Manohar Parrikar said in a written reply to Dharmendra Yadav and ShrirangappaBarne in the Lok Sabha.

What exactly is Project 75?

Project 75 was for construction of six submarines based on a Western design and six submarines of a design sourced from Eastern origin (Russia included) under Project 75(I) were to be constructed with the participation of the Indian industry both, private and public, explained Indian Defence Review.

For the project, a contract with Thales/DCNS International was concluded to construct six submarines based on the Scorpene design at MDL in October 2005. The submarines are highly sophisticated and of contemporary design. The weapons envisaged on these platforms are state-of-the-art torpedoes and the Exocet anti-ship missile.

Things don’t look good for Project 75(I), with indiandefencereview.com saying that the project has been inordinately delayed.

As far as Project 75 are concerned, it seems to be on track.

On July 21, 2017, Subhash Bhamre, minister of state in the defence ministry, told the Lok Sabha that six submarines are under construction under Project 75 at the Mazagon Dock Shipbuilders Ltd, Mumbai.

“The first submarine is scheduled to be delivered in August, 2017. The second submarine was launched in January 2017 and is scheduled for delivery in December, 2017. The induction of the Kalvari class submarines will enhance the capabilities of the Indian Navy to meet envisaged threats and missions,” said Bhamre.

The submarine dedicated to the nation on Thursday was handed over for extensive sea trials. Only after extensive tests, is it being put to use.

PIB in April 2015 reported that Kalvari, first of the Indian Navy’s Scorpene class stealth submarines being built under the Project 75, under collaboration with M/s DCNS, France, had achieved a major milestone with her ‘undocking’ at the Mazagon Dock Limited (MDL).

The project 75, which by then had already seen a delay of almost 40 months, was brought on track and the delivery schedule for the successive submarines was reduced. Parrikar had then asked the defence public sector yards viz. Mazagon Docks Limited and Goa shipyard to double their production in the coming three years.             

The Scorpene submarines would pack a potent punch. She would be equipped with anti-ship missiles and long range guided torpedoes along with modern sensor suite.
 

Comments

 

Other News

Harnessing the demographic capital: how effective are skilling programmes?

Probing data concerning increased job creation and the decline in unemployment has been holding the attention of economists and been subject of discussions in several think tanks in the preceding months. The NITI Aayog reports that 3.53 million new jobs were created between September 2017 and February 2018

It`s time to Unlock now, with economic focus

With Lockdown 4 ending Sunday, the home ministry has issued new guidelines to fight COVID-19 and for phased re-opening of areas outside the Containment Zones. The guidelines, issued based on extensive consultations held with states and UTs, will be effective from June 1 till June 30. The first phase of reo

Small kitchen gardens turn saviours for Gujarat tribal families

When the whole world is fighting COVID-19, food and nutrition security has become a major issue. The pandemic has aggravated the existing food crisis in India, especially in rural and tribal regions. There has been less availability of fresh foods in most parts of the country, and the tribal community has

India will set example of post-Covid-19 economic revival: Modi

India is determined to “set an example” for the rest of the word in the post-pandemic economic revival, prime minister Narendra Modi has said, underling the need to become self-reliant. “There is also a widespread debate on how the economies of various countries, including

3,543 ‘Shramik Special’ trains transport 48 lakh people in 26 days

Close to 48 lakh migrant labourers have been able to reach home from the cities they were working in, as the Indian Railways have run a total of 3,543 “Sharmik Special” trains from May 1. Following the home ministry order regarding the movement by special trains of migrant worker

How Jeevan Raths have helped 52,000 migrants in Maharashtra

Before the novel coronavirus hit it, Mumbai about 10-12 lakh labourers from elsewhere had made it their home. The figure for the state of Maharashtra was another 18-20 lakh. As the pandemic spread and the Maximum City emerged as the worst-hit place in India, all economic activities came to an end, and with



Archives

Current Issue

Opinion

Facebook    Twitter    Google Plus    Linkedin    Subscribe Newsletter

Twitter