Shortcomings spotted in fuel management at NTPC power stations

CAG says NTPC agreed to pay performance incentive for supplies above 90 percent of Annual Contracted Quantity. This increased fuel cost of 10 stations by Rs 558 crore

GN Bureau | February 6, 2017


#power generation   #coal   #NTPC  


Three power stations of NTPC, India’s largest power utility, incurred an extra expenditure of Rs 2,483.39 crore due to procurement of coal through costly sources during the period from 2010-11 to 2015-16, noted an audit report.
 
The report of the Comptroller and Auditor General of India (CAG) on fuel management of coal based power stations of NTPC Limited said that the installed electricity generation capacity in the country as on October 31, 2016 was 307,278 MW out of which coal based capacity was 186,493 MW (60.69 percent). NTPC Limited’s coal based capacity is 40,084 MW (October 2016).
 
Coal cost constitutes 60 to 70 percent of the total generation tariff of a coal based power station and has a major impact on cost of supply of power to consumers. Inefficiencies in fuel management would increase the energy charges for the stations and cost of power to the ultimate consumer. The performance audit covers fuel management of 13 out of 26 coal based power stations of NTPC Limited and its joint ventures during the period from April 2010 to March 2016.
 
 
The CAG report said that coal is primarily procured domestically through long term coal linkages from subsidiary companies of Coal India Limited (CIL) and Singareni Collieries Company Limited (SCCL) at notified rates. For all other procurements, such as procurement through MOU, e-auction and import, the rates are higher.
 
“Examination of fuel linkages revealed that two power stations, viz., Barh-II and Kahalgaon-II, were operating without long term fuel linkage while Ramagundam-III was operating with reduced linkage. The three stations incurred an extra expenditure of Rs 2,483.39 crore due to procurement of coal through costly sources during the period from 2010-11 to 2015-16. Fuel Supply Agreement (FSA) on cost-plus basis was agreed to for Mouda station though New Coal Distribution Policy did not mandate it. Coal supplied under cost-plus agreement was costlier than notified rates and resulted in extra fuel cost for Mouda station to the extent of Rs 31.11 crore from February 2015 to March 2016.”
 
 
It noted delay in signing FSA. “There were significant time gaps between Commercial Operation Date and signing of FSA in five stations, viz., Sipat-I, Rihand-III, Farakka-III, Vindhyachal-IV and Korba-III, which forced these stations to procure coal under ‘Performance Incentive’ provision of the FSA of older units, incurring additional fuel cost of Rs 323.37 crore.”
 
As per New Coal Distribution Policy, 100 percent of the Annual Contracted Quantity (ACQ) as per the normative requirement of the consumers would be supplied through FSA at notified prices. However, NTPC agreed to pay performance incentive for supplies above 90 percent of ACQ. This increased fuel cost of 10 stations by Rs 558 crore.
 
FSA for stations commissioned after March 31, 2009 provided for payment of performance incentive on Deemed Delivered Quantity, which included imported coal not actually delivered to the station. The payment of performance incentive for such notional deliveries increased the outgo of two power stations (Vindhyachal and Rihand) by Rs 18.43 crore for the year 2013-14 without any commensurate benefit.
 
 
On non-recovery of compensation for short supplies under FSAs, the CAG report said that the FSAs provided monetary compensation for short delivery by coal companies as well as short lifting by power stations. Performance incentive was also payable by power stations for annual supplies above 90 percent of ACQ. In the case of three stations, viz., Badarpur, Jhajjar and Ramagundum, though these stations paid incentive of Rs 128.08 crore, compensation amounting to Rs 114.68 crore could not be recovered from coal companies. In the case of Vallur station, though there was significant short supply, compensation was not even claimed.
 
The report said that in addition to FSAs, power stations entered into Memoranda of Understanding (MOUs) with coal companies to supplement coal supplies. Procurement of coal through MOUs was not mandated under New Coal Distribution Policy. High premium was being paid for MOU procurements, even compared to maximum incentive of 40 percent over notified rates under FSA. Premium agreed to by NTPC under MOU with Singareni Collieries Company Limited was higher than FSA rates by Rs 1600.64 crore while the premium agreed to under the MOU with ECL was higher by Rs 1,433.19 crore.
 
Read: Report of the Comptroller and Auditor General of India on Fuel Management of Coal Based Power Stations of NTPC Limited
 
 
 
 
 

Comments

 

Other News

The Constitution cannot be altered: Justice Abhay Oka

Justice Abhay Oka, who retired from the Supreme Court in May 2025, has said that the Constitution of India cannot be altered. Explaining the landmark Kesavananda Bharati judgment (1973) on the basic structure of the Constitution, he said, “This is one judgment that has saved democracy in India.&rdq

How the flora and fauna evolved in the Indian subcontinent

Mammals of India  By A.J.T. Johnsingh and P.O. Nameer HarperCollins India in association with Bombay Natural History Society  

India`s renewable race is moving beyond megawatts

When Shell bought Sprng Energy in 2022, India`s renewable energy market appeared to offer precisely what global energy majors were seeking: scale, growth and a place in one of the world`s largest energy transitions. Four years later, Shell is selling the same business to Aditya Birla Group for an enterpris

Nepal Floods: India keeps close watch on the situation

India`s central government has been keeping a close watch on the situation arising out of the flash flood in Nepal on Wednesday. Union home minister Amit Shah spoke with the chief ministers of Bihar and Uttar Pradesh, the two states that share the border with Nepal, regarding the disaster

UPI completes 10 years of digital payments revolution

The Unified Payments Interface (UPI), launched on August 25, 2016 by the National Payments Corporation of India (NPCI) under the regulatory oversight of the Reserve Bank of India (RBI), has completed 10 years of transforming digital payments in India. UPI has emerged as the backbone of India’s digi

Here’s an I.D.E.A. for career growth and success

Success in today’s professional organisation is no longer solely determined by academic qualifications, technical expertise or years of experience. While these attributes do matter, organisations increasingly value individuals who demonstrate the right mindset and behavioural qualities. The ability

Upcoming Conferences



-->

Archives

Current Issue

Opinion

Facebook Twitter Google Plus Linkedin Subscribe Newsletter

Twitter